Results

A ground-source heat pump of 8 kW needs about 140 m of borehole (2 × 70 m) in “Average soil / rock (λ ≈ 2 W/mK)” at ~47 W/m. SCOP ≈ 4.23, and it costs 141 €/yr less to run than an air-source unit. The length is set by the annual-energy limit (~100 kWh per metre per year) rather than by peak power, to avoid cooling the ground over the years.
Total borehole length
140m
2 boreholes × 70 m · 47 W/m
Heat pump size
8kW
design heat loss 7 kW at -9 °C
Seasonal COP (SCOP)
4.23
air-source equivalent 3.79
Running cost
€1,216
4,342 kWh of electricity per year
Saving vs air source
€141
Saving vs gas boiler
€825
gas 2,041 €/yr at 90% efficiency
Estimated installed cost
€21,818
ground loop 9,818 + unit 12,000
Heat extracted from ground
14,026kWh/yr
100 kWh per m of borehole
Full-load hours
2,296h/yr
Annual heat delivered
18,368kWh
CO₂ per year
1.52t
vs 3.73 t with gas
Ground temperature
11.4°C
Berlin, Germany
Monthly electricity: ground vs air source
Borehole length by ground type

Ground types (VDI 4640 indicative extraction rates)

GroundBorehole W/m (1,800 h)W/m (2,400 h)Horizontal W/m² (1,800 h)Borehole needed (m)Loop area (m²)
Dry gravel / sand252012293642
Moist clay / loam453528166265
Water-saturated gravel / sand706038140234
Limestone (massive)625230140244
Sandstone726030140244
Granite / gneiss756330140244
Basalt524530140244
Average soil / rock (λ ≈ 2 W/mK)554525140293
  • Extraction rates are VDI 4640 indicative values for small systems (< 30 kW) without groundwater flow. For the final design, use a thermal response test and an EED/GLHEPro-type simulation, or the MCS MIS 3005 tables.
  • Borehole length is the larger of the peak-power criterion (W/m) and an annual energy limit of 100 kWh/m (60 kWh/m² for horizontal loops). Boreholes are usually spaced at least 6 m apart. Horizontal loops need roughly 1.5–2× the heated floor area in free land.
  • Climate: Berlin, Germany. In the heating season the brine runs ~4–8 K below the undisturbed ground temperature.

Free calculator by GreenEnergy.net