Results

54 MW producing 173,887 MWh/yr (net CF 36.8%). LCOE 54 €/MWh vs a 68 €/MWh price. Bankable-looking: equity IRR 20.3%, minimum DSCR 1.75.
Annual energy (P50, year 1)
173.9GWh
48,302 average EU homes
Net capacity factor
36.8%
gross 43.2% · 3,220 full-load h
LCOE
54€/MWh
at 6.5% WACC over 30 years
Project IRR (unlevered)
12.6%
NPV 55 M€
Equity IRR
20.3%
70% debt at 5.5% over 15 years
Min / avg DSCR
1.75 / 1.85
debt service 5.27 M€/yr
Total capex
€75,600,000
435 € per annual MWh
Year-1 revenue
€11,824,328
opex 2,615,774 €
Simple payback
8 yrs
Wind farm area
6.4km²
rotor Ø 138 m · direct footprint ≈ 22 ha
CO₂ avoided per year
69.6kt
Cash flow: revenue, opex, debt service
LCOE breakdown

Project cash flows

YearEnergy (MWh)Revenue (k€)Opex (k€)CFADS (k€)Debt service (k€)DSCREquity cash (k€)
1173,88711,8242,6169,2095,2721.753,936
2173,19211,9542,6679,2875,2721.764,015
3172,49912,0842,7199,3665,2721.784,094
4171,80912,2172,7719,4455,2721.794,173
5171,12212,3502,8259,5255,2721.814,253
6170,43712,4852,8809,6055,2721.824,333
7169,75512,6222,9369,6865,2721.844,413
8169,07612,7602,9949,7665,2721.854,494
9168,40012,9003,0529,8485,2721.874,576
10167,72613,0413,1119,9295,2721.884,657
11167,05613,1833,17210,0125,2721.94,739
12166,38713,3283,23410,0945,2721.914,822
13165,72213,4743,29710,1775,2721.934,905
14165,05913,6213,36110,2605,2721.954,988
15164,39913,7703,42610,3445,2721.965,071
16163,74113,9213,49310,427——10,427
17163,08614,0733,56110,512——10,512
18162,43414,2273,63110,596——10,596
19161,78414,3823,70110,681——10,681
20161,13714,5403,77410,766——10,766
21160,49214,6993,84710,852——10,852
22159,85014,8603,92210,938——10,938
23159,21115,0223,99911,024——11,024
24158,57415,1874,07711,110——11,110
25157,94015,3534,15611,197——11,197
26157,30815,5214,23711,284——11,284
27156,67915,6904,32011,371——11,371
28156,05215,8624,40411,458——11,458
29155,42816,0364,49011,546——11,546
30154,80616,2116,7379,474——9,474
  • Energy from a generic 4.5 MW power curve (rotor Ø 138 m, air density 1.188 kg/m³) under a Weibull distribution, minus 15% total losses. Use the turbine supplier’s curve and a wake model (e.g. PyWake, WAsP) for a bankable P50.
  • Pre-tax model: corporate tax, depreciation, grid fees, balancing costs and curtailment are not included. Lenders size debt on P90 (typically 8–12% below P50), so test a lower capacity factor.
  • Land: the array area spans the whole layout; only about 1–3% of it is physically occupied (pads, roads, substation), and farming continues around the turbines.